For 30 years governments have talked about an Eastern Busway from Brisbane to Capalaba, but only one kilometre of the planned 17.7kms route has been delivered. At this rate, it would take at least 501 years to get the job finished.
Recently, Brisbane City Council kicked off a business case study into expanding its Brisbane Metro service north, south, and east to Capalaba. The study is expected to take two years and cost $150 million, including $50 million provided by the Federal Government.

Federal MP for Bowman Henry Pike says he’s “been pushing hard to get the Brisbane Metro extended to Capalaba”. He told Federal Parliament in August 2025 that with fast electric vehicles running on busways with no traffic lights, the Metro could halve the current 45 minutes trip time it takes for a bus to get from Capalaba to Brisbane, and that the Metro could be “locked in as part of the Brisbane 2032 Olympic legacy”.
So how likely is it that people will be zooming from Capalaba to Brisbane in 22.5 minutes on a Brisbane Metro service, before the Olympic torch is lit in 2032?
To answer this question we need to understand a few things about busways, transitways, the Brisbane Metro, and business case assessments.
The Eastern Busway
The concept of a busway linking Capalaba to Brisbane was first developed in the 1990s by Brisbane City Council and the Queensland Government as a way of moving more commuters from the suburbs into the city centre, without widening arterial roadways or developing more train lines.
A busway route from Buranda to Capalaba alongside Old Cleveland Road was investigated by consultants Connell Wagner for the Queensland Government in 2006-2007. Their Concept Design and Impact Management Plan report shows a detailed 17.7 kms route including a suggested construction method for each section – using tunnels and bridges where necessary.
The consultants noted that while the whole route to Capalaba would ultimately be a dedicated busway, this could be developed in stages starting with sections close to the centre of Brisbane. Other sections might be delivered (more economically) as transit lanes in the short to medium term.
From 2009 to 2011 the Bligh Labor Government spent $466 million developing a 1.05 km section of the Eastern Busway from Buranda to Main Road Coorparoo, with new busway stations at Stones Corner and Langlands Park. Stated benefits for bus passengers included avoidance of four sets of traffic lights with a travel time reduction of up to eight minutes during peak hours.

The next section of the Eastern Busway, would reach Bennetts Road in Coorparoo, a distance of about 1.5kms. Works would include new busway stations at Coorparoo Junction (the Old Myer Centre) and Bridgewater North near Bennetts Road.
The Connell Wagner report shows that this section of the Busway would be constructed mostly underground, using driven (bored) tunnels.
The Queensland Government asked the Federal Government in 2008/09 to fund 100% of the required $685 million which is equivalent to about $1.1 billion in today’s dollars if adjusted using the ABS CPI index (Brisbane). The benefit/cost ratio was unfavourable, so Federal funding was not approved.
From Bennetts Road in Coorparoo, the Busway could be extended another 2.4 kms east to new Busway stations at Camp Hill and Carina. About two kilometres of tunnel would be needed for this section, transitioning to surface level busway on the old tramline route near Carina.
After Carina, above ground busways would connect to a new busway station at the northern end of Carindale Shopping Centre – a distance of about 1.8 kms including a busway bridge over busy Creek Road.
So extending the Eastern Busway about 5.7 kms from its current terminus at Langlands Park to Carindale Shopping Centre might involve 3.5kms of tunnel work, a bridge over Creek Road and construction of five new busway stations. In Queensland’s overheated construction market, this part of the Eastern Busway would likely cost several billion dollars to build.
An alternative to busway tunnels in Coorparoo and Camp Hill would be to resume land next to old Cleveland Road for surface level busways, about 10 metres wide for one lane each way. Surface busways may be less expensive, but to avoid traffic light delays at various intersections along Old Cleveland Road (such as at Cavendish Road and Bennetts Road) several overpasses would be required.
Morphing from the Eastern Busway to the Eastern Transitway
Following the 2012 election of Campbell Newman’s LNP Government, not much more was said or done about extending the Eastern Busway.
When back in office (2015 to 2024), Labor State Governments couldn’t afford to build further sections of the Eastern Busway. In 2020 the Transport Department announced that the Eastern Transitway project would focus on introducing sections of priority bus lanes along Old Cleveland Road.
Stage 1 of the Eastern Transitway project, between Narracott and Carindale streets, was completed in 2023-24 at a cost of $30 million.
Brisbane Metro

The Brisbane Metro is a bus service operating currently on two busy busway routes:
- M1 traveling 17kms from Eight Mile Plains to Roma Street in 34 minutes, with service departing every five minutes in peak hours; and
- M2 traveling 9.7kms from Royal Brisbane & Womens Hospital to the University of Queensland in 32 minutes, with services every ten minutes.
Brisbane Metro vehicles are 24.4 metre long battery electric powered bi-articulated (bendy) buses with a train like appearance. In normal mode they can carry 150 passengers with 64 seated and 86 standing. In event (crush) mode the vehicles can carry up to 170 passengers.
Brisbane City Council has bought 60 of these Metro vehicles at a reported cost of $190 million including charging facilities (plus undisclosed cost increases) giving a likely average cost per vehicle of more than $3 million.

Assessing a business case for Brisbane Metro expansions
The Brisbane Metro business case study might include activities such as:
- Review current bus operations, previous busway studies, values of properties that might have to be resumed
- Assess likely car traffic and bus passenger demand north, south and east of central Brisbane over the next 20-30 years
- Examine alternative busway routes and construction methods, do preliminary impact analysis, and update cost estimates
- Investigate alternative vehicle options then estimate capital and operating costs
- Shortlist possible route extension cases
- Estimate travel times and service frequency for these cases
- Compare various cases and combinations of cases with a financial model
Route extension business cases will be assessed on how much benefit they deliver such as increased numbers of passengers and reduced travel times, compared with the cost of building new busways and purchasing new vehicles.
The low hanging fruit will be route extension cases that don’t require massive investment in new busways.
So when will Capalaba get the Brisbane Metro and the Eastern Busway?
In short, when one or more governments thinks it’s worth spending several billion dollars on this project, instead of other vote-winning projects.